Northampton, UK-based crane rental company Berry Cranes Ltd. recently used an all-terrain crane rigged with a one-over-two Modulift spreader beams to lift a wooden bus shelter at the Bicester Village shopping outlet in Oxfordshire.
Berry was tasked to lift the fragile 14-ton bus shelter from its roadside location, relocate it to a storage area half a mile away, and eventually return it to another location at the retail village. It had to be moved to accommodate important roadworks at its original position. Integral to the operation was three spreader beams from below-the-hook equipment manufacturer Modulift.
Equipment Used
Berry chose a Tadano ATF 70-G4 from its 12-crane fleet, a MOD 24 spreader beam, two MOD 12s spreader beams, and a variety of other rigging equipment to complete the initial lift. The same equipment will be employed when it’s time to reposition the bus shelter in due course. The crane used 94 feet (30 meters) of main boom, which provided 25.5-ton-capacity at a 20-foot (6-meter) radius.
Greg Allen, contract lift operations manager at Berry Cranes, said: “The biggest issue was that the bus shelter was originally built on site during the 1960s so no-one could know how stable it was until we lifted it. Further, the lift required extensive planning, as the location gets extremely busy during hours when the retail park is open to shoppers.”
Berry provided a crane operator, lift supervisor, and two riggers, while the client supplied a structural engineer and two carpenters. Special steel beams were manufactured and placed underneath the structure, creating a cradle for the load as it was lifted. Prior to delivery to site the beams were tested in accordance with Lifting Operations and Lifting Equipment Regulations (LOLER) 1998.
Site Challenges
Before the lift, the ground was dug from beneath the bus shelter in two positions to allow contractors to slide two beams lengthways underneath the structure. Jacks were used to lift the large beams with the shelter sitting on them to allow four smaller beams to be slid widthways underneath the larger ones. Fabricators then installed lifting bolts onto the ends of the smaller beams to attach the shackles.
Berry used the MOD 24 spreader beam at 18 feet (5.5 meters); it can lift up to 27 tons at 17 feet (24t at 5 meters) and used up to 26 feet (8 meters) at lower capacities. The pair of MOD 12 beams was used at 13 feet (4 meters); they are capable of lifting 13.4 tons at 15 feet (12t at 4.75 meters), while lower capacities are possible up to 21 ft. (6.5 meters). The beams and additional rigging equipment, including a variety of slings and shackles, were sourced from Berry’s extensive below-the-hook stock.
One-over-two spreader beam configurations are particularly common when there are four lifting points. However, in this case, Berry attached two slings at each of the four corners of the rig to connect to shackles and the steel beams beneath the bus shelter.
Allen concluded: “Combining expertise and quality equipment, we were able to complete the project safely and efficiently, only closing a small area of the car park to complete the lift and escort the load away from the site on specialized transport.”